Indian Point’s very, very bad year
June 8, 2016
- In June, a mylar balloon floated into a switchyard, causing an electrical disturbance resulting in the shutdown of the Unit 3 reactor.
- In July, the Unit 3 reactor was shut down after a water pump failure.
- In December, the Unit 2 reactor was forced to shut down after several of the reactor's control rods lost power.
- In December, a string of droppings from a large bird damaged outdoor transmission insulators connected to the Unit 3 reactor, creating an electrical disturbance causing the reactor’s automatic shutdown to trip.
- Also in December, an electrical anomaly caused the Indian Point 3 reactor to shut down. In response, Gov. Andrew Cuomo said that because there had been a “number of recent unplanned outages” there will be “increased inspections and scrutiny” at the site.
- In February, Entergy reported a severe spike in radioactive, tritium-contaminated water leaked into the groundwater at the facility. Alarming levels of radioactivity were reported at three Indian Point monitoring wells, including one where levels rose 65,000 percent from 12,300 picocuries per liter to over 8 million picocuries per liter. Follow-up tests indicated that the highest concentration was 80 percent higher than what was reported only a few days earlier.
- During plant refueling in March, a breaker tripped and cut power in one of the reactors. The diesel back-up also failed. A second backup system, fortunately, worked.
- Also in March, an inspection found that 227 of the 832 bolts that hold the inner plates of the reactor core together were found to be missing or damaged. Entergy, in a report to the US Nuclear Regulatory Commission admitted this to be a condition that “significantly degrades plant safety.” This damage to Indian Point Reactor 2’s core is four times worse than any similar problem ever seen at any other American nuclear reactor and experts believe that it could result in a lack of structural stability in the reactor.
- In May, NRC ruled that its analysis of the costs of a severe accident at Indian Point was misleading, used erroneous data and was in violation of the National Environmental Policy Act. Another analysis will need to be conducted.
- The NRC says one of Indian Point's reactors has the highest risk of earthquake damage of all the nation's reactors.
- Federal studies have shown that the plant is severely vulnerable to terrorism.
- Indian Point has 2,000 tons of radioactive waste overpacked into leaking spent-fuel pools.
- The evacuation plan in the wake of a catastrophic incident is unworkable. Tens of millions of people would be sitting ducks in the event of a disaster.
Related campaigns
Beyond Indian Point
Monitoring the shutdown of a nuclear power plant on the banks of the Hudson that killed billions of fish each year
Spill prevention and preparedness
Working to protect the Hudson and its communities from the threats posed by anchor strikes and spills
Saving Hudson River fish
Protecting iconic species vital to our local ecosystems